GeoSS recommends achieving two consistent sets before final termination. 4. Ground Monitoring and Mitigation
Pile testing must be conducted under the direct supervision of a designated person . GeoSS recommends achieving two consistent sets before final
by releasing the pressure to zero and re-jacking before final termination. Equipment Limits: Jacking machines should ideally be used up to only 75% of their maximum capacity to maintain stability and safety. Essential "Good Practices" for Site Success GeoSS recommends achieving two consistent sets before final